L Tower Construction Schedule November 19 – 23

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 19 – 23, 2012

Updated  November 20, 2012

Monday, November 19

  • Drywall delivery starting at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.

Tuesday, November 20

  • A rebar (steel) delivery starting at 7:00 am.
  • Miscellaneous construction activities throughout the day.

Wednesday, November 21

  • Drywall delivery starting at 7:00 am.
  • One container of windows with delivery starting at 7:30 am.
  • Miscellaneous construction activities throughout the day.

Thursday, November 22

  • A rebar (steel) delivery starting at 7:00 am..
  • Electrical materials delivery starting at 8:00 am.
  • Three containers of windows with delivery starting at 10:00 am.

Friday, November 23

  • A delivery of duct work delivery starting at 7:00 am.
  • Electrical materials delivery starting at 8:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 19 – 23

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: