L Tower Construction Schedule November 12 – 16
November 9, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for November 12 – 16, 2012
Posted November 9, 2012
Monday, November 12
- A delivery of 3 containers of window/curtain wall between 7:00 am and 4:00 pm
Tuesday, November 13
- A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
Wednesday, November 14
- A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
Thursday, November 15
- A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
- A rebar (steel) delivery starting at 12:30 pm.
- Please note:
- There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
Friday, November 16
- No scheduled work at this time.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.