L Tower Construction Schedule November 12 – 16

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 12 – 16, 2012

Posted November 9, 2012

Monday, November 12

  • A delivery of 3 containers of window/curtain wall between 7:00 am and 4:00 pm

Tuesday, November 13

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Wednesday, November 14

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Thursday, November 15

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, November 16

  • No scheduled work at this time.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 12 – 16

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: