Backstage Construction Schedule – November 10 – 16

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 10 – 16, 2012

Posted November 9

Saturday, November 10

Daytime Vehicular Road Closure

  • A daytime vehicular road closure will be maintained Saturday from 9:00 am to 7:00 pm to permit repaving the new vehicle lane. 

Daily – November 12 – 16

  • No work work is currently scheduled for the Backstage and L Tower Parking Site this week.

Roadway Realingment

Eastbound Vehicle lane being installed on The Esplanade 11/9/12

Pedestrian route being installed on The Esplanade 11/9/12

The new pedestrian route through the site will provide 2.11 metres or approximately 7 feet of pedestrian space fenced on the south side and protected from vehicular traffic on the north side by concrete jersey barriers. 

The new eastbound vehicle lane is 3.3. metres or 10 feet 10 inches wide. 

t
t
t

UPDATE on water-main and sanitary sewer work: 

City of Toronto subcontractor OJCR Construction will be visiting the site this week to review how they will work with the new roadway alignment. It is expected that OJCR will be submitting an application for a road closure permit next week to enable them to so the sanitary sewer and water-main connection work for the Backstage site. The start date for their work is not yet know. While OJCR is working a safe pedestrian route will be maintained. Vehicular traffic will be re-routed via Yonge and Front to Scott Street. 

 NOTES: 

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 12 – 16

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: