Backstage Construction Schedule – November 5 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 5 – 9, 2012

Posted November 2

Daytime Road Closure and Roadway Realignment

A daytime road closure is scheduled for Friday November 9, from 9:00 am to 8:30 pm. This has been discussed with and approved by City Councillor McConnell and reviewed with representatives of the neighbouring condos and businesses. The daytime road closure is to permit the installation of a new alignment of the vehicular and pedestrian routes between Yonge Street and the driveway into the Toronto Parking Authority garage, west of Scott Street. The roadway realignment will provide for a separated and protected pedestrian walkway and 1 eastbound vehicular lane. More detailed information will be provided next week. 

Monday, November 5

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Tuesday, November 6

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Wednesday, November 7

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Thursday, November 8

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Friday, November 9 – Road Closure 9:00 am to 8:30 pm

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.
  • Roadway realignment.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Nov 5-9

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: