Backstage Construction Schedule – December 3 – December 7
November 30, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 3 – December 7, 2012
Updated December 4, 2012
Monday, December 3
- CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
- OJCR will be working on service connection on the Esplanade.
Tuesday, December 4
- CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
- OJCR will be working on service connection on the Esplanade.
Wednesday, December 5
- The Long Reach back-hoe will be delivered to the site midday under police escort
- OJCR will be tying in water lines on the Esplanade.
Thursday, December 6
- GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
- OJCR will be tying in water lines on the Esplanade.
Friday, December 7
- GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
- OJCR will be tying in water lines on the Esplanade.
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7