Backstage Construction Schedule – October 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 15 – 19, 2012

Posted October 12, 2012

Monday, October 15 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Tuesday, October 16 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Wednesday, October 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Thursday, October 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm

Friday, October 19

  • Subcontractor, GFL Excavating will be removing material from the site: six(6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

L Tower Construction Schedule October 6 – 12

This is the current construction schedule for 8 The Esplanade – L Tower – for October 6 – 12, 2012

Posted October 5, 2012

The L Tower Celebrates it’s topping-off on Wednesday. 

Saturday, October 6

  • Washroom Servicing 9:00 am to Noon.

Sunday, October 7

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity.

Monday, October 8 – THANKSGIVING DAY

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity. 

Tuesday, October 9

  • Delivery of elevator equipment from the Yonge Street gate. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 10

  • L Tower Topping-Off Ceremony at 1:00 pm. 

Thursday, October 11

  • Hoist lift – three (3) floors.

Friday, October 12

  • TBD – please check back for updates. 

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 6-12

Backstage Construction Schedule – October 9 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 9 – 12, 2012

Posted October 5, 2012

Monday, October 8 – THANKSGIVING DAY

Tuesday, October 9 

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 10

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 6-12