Backstage Construction Schedule – October 29 – November 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 27 – November 2, 2012

Posted October 26, 2012

Monday, October 29

  •  GFL Excavating will have one machine breaking shale with the hydraulic breaker until no later than 7:00pm.

At this point the excavating operation will be on hold for three weeks until hoarding realignment has been completed. There maybe some sporadic activity in the following weeks as GFL Excavating completes their work.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: