L Tower Construction Schedule October 20 – 26

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 20 – 26, 2012

Updated October 24, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 20

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 1 container of curtain wall between 9:00 am and 12:00 pm.
  • UECL to service the hoist between 9:00 am and 12:00 pm.

Monday, October 22

  • A 4.5M (cubic metre) concrete pour starting at 1:00 pm

Tuesday, October 23

  • CANCELLED due to rain: A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 24

  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, October 25

  • Rebar delivery at 12:30 pm. – cancelled

Friday, October 26

  • Rescheduled from October 24: A 200CM (cubic metre) slab concrete pour at level 60, starting 8:00 am, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 7:00 am.cancelled
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: