L Tower Construction Schedule October 13 – 19

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 13 – 19, 2012

Updated October 16, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 13

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 3 containers of curtain wall between 9:00 am and 4:00 pm.

Monday, October 15 

  • Rebar delivery at 7:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 1:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, October 16

  • Rebar delivery at 7:00 am. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 17

  • Generator removal and pick-up after 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while teh generator is removed and loaded out.

Thursday, October 18

  • Rebar delivery at 7:00 am.
  • A delivery of four containers of windows.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, October 19

  • Hoist maintenance from 8:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 12:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: