Backstage Construction Schedule – October 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 15 – 19, 2012

Posted October 12, 2012

Monday, October 15 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Tuesday, October 16 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Wednesday, October 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Thursday, October 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm

Friday, October 19

  • Subcontractor, GFL Excavating will be removing material from the site: six(6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: