Backstage Construction Schedule – October 29 – November 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 27 – November 2, 2012

Posted October 26, 2012

Monday, October 29

  •  GFL Excavating will have one machine breaking shale with the hydraulic breaker until no later than 7:00pm.

At this point the excavating operation will be on hold for three weeks until hoarding realignment has been completed. There maybe some sporadic activity in the following weeks as GFL Excavating completes their work.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

L Tower Construction Schedule October 27 – November 2

This is the current construction schedule for 8 The Esplanade – L Tower – for October 27 – November 2, 2012

Posted October 26, 2012

Saturday, October 27

  • A delivery of 2 containers of window/curtain wall between 9:00 am and 2:00 pm

Monday, October 29

  • There will be a platform removal
  • A rebar (steel) delivery starting at 12:30 pm.

Tuesday, October 30

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, October 31

  • The boom crane will be on site to move concrete pump.
  • A rebar (steel) delivery starting at 12:30 pm.

Thursday, November 1

  • A rebar (steel) delivery starting at 12:30 pm.

Friday, November 2

  • A rebar (steel) delivery starting at 7:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

L Tower UPDATE for Friday, October 26

UDPATE

Friday, October 26

  • Rescheduled from October 24: A 200CM (cubic metre) slab concrete pour at level 60, starting 8:00 am, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 7:00 am. – cancelled

Update: No date set for Water & Sanitary Sewer work on The Esplanade

UPDATE: Water & Sanitary Drain Work on The Esplanade – City Contractor is still in the process of applying for a road closure on The Esplanade.

The Construction Management Team was advised late last week that City of Toronto contractor OJCR Construction is planning to install water connections, sanitary drain connections and storm water connections at 1 The Esplanade (Backstage).

This would involve OJCR Construction closing the Esplanade to dig and make connections. The affected area would be between the western entrance to the Toronto Parking Authority garage and Yonge Street.

The Construction Management Team has been advised that OJCR plans have been further delayed. No start date is currently available.

The work is required as part of construction but its scheduling is in the hands OJCR Construction and the City of Toronto.

We have been in active dialogue with the City Councillor’s Office. They are seeking more detailed information from City staff. We will post details when we have them.

Backstage Construction Schedule – October 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 22 – 26, 2012

Updated October 24, 2012

Please note efforts are being made to ensure pedestrian safety as dump trucks access the site. Traffic control staff are on site and safety cones will be placed on the sidewalk and roadway to indicate the pedestrian route through the work zone. Starting November 9, a new alignment of the vehicular and pedestrian routes will be put in place, providing enhanced safety. More information will be provided next week. 

Monday, October 22 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Tuesday, October 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Wednesday, October 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Thursday, October 25

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Friday, October 26

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

L Tower Construction Schedule October 20 – 26

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 20 – 26, 2012

Updated October 24, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 20

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 1 container of curtain wall between 9:00 am and 12:00 pm.
  • UECL to service the hoist between 9:00 am and 12:00 pm.

Monday, October 22

  • A 4.5M (cubic metre) concrete pour starting at 1:00 pm

Tuesday, October 23

  • CANCELLED due to rain: A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 24

  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, October 25

  • Rebar delivery at 12:30 pm. – cancelled

Friday, October 26

  • Rescheduled from October 24: A 200CM (cubic metre) slab concrete pour at level 60, starting 8:00 am, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 7:00 am.cancelled
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

L Tower Concrete Pour cancelled

The 200 cubic metre slab concrete pour scheduled for today–October 23, 2012–has been cancelled due to rain.

It will be rescheduled to Friday, October 26, weather permitting.

Water & Sanitary Drain Work on The Esplanade

Water & Sanitary Drain Work on The Esplanade – City Contractor is applying for a road closure on The Esplanade.

The Construction Management Team has been advised late today that City of Toronto contractor OJCR Construction is planning to install water connections, sanitary drain connections and storm water connections at 1 The Esplanade (Backstage) next week.

This would involve OJCR Construction closing the Esplanade for a up to a week to dig and make connections. The affected area would be between the western entrance to the Toronto Parking Authority garage and Yonge Street.

The Construction Management Team has been advised that OJCR plans to start work on Wednesday October 24 pending approval of their application for a road closure permit.

The work is required as part of construction but its scheduling is in the hands OJCR Construction and the City of Toronto.

We have advised the City Councillor’s Office. More information should be available on Monday.

Updates for L Tower Construction – October 17 – 19

Please note that updates for the L Tower’s construction schedule for Wednesday October 17 through Friday October 19 have been posted.

Please click here to see them.

L Tower Construction Schedule October 13 – 19

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 13 – 19, 2012

Updated October 16, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 13

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 3 containers of curtain wall between 9:00 am and 4:00 pm.

Monday, October 15 

  • Rebar delivery at 7:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 1:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, October 16

  • Rebar delivery at 7:00 am. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 17

  • Generator removal and pick-up after 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while teh generator is removed and loaded out.

Thursday, October 18

  • Rebar delivery at 7:00 am.
  • A delivery of four containers of windows.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, October 19

  • Hoist maintenance from 8:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 12:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

%d bloggers like this: