Backstage Construction Schedule – September 17 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 17 – 21, 2012

Updated September 16, 2012

NOTE: Further details on the daytime road closures will be posted on Monday, September 17

Monday, September 17 

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, September 18 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions. 
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Wednesday, September 19 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Thursday, September 20 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Friday, September 21– Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. * 
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

L Tower Construction Schedule September 17 – 21

This is the current construction schedule for 8 The Esplanade – L Tower – for September 17 – 21, 2012

Updated September 18, 2012

Monday, September 17 

  • A delivery of heat pumps at 7:00 am. 
  • A second delivery of heat pumps at 10:00 am. 
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, September 18

  • A delivery of drywall and metal studs starting at 8:00 am.
  • A second delivery of drywall and metal studs starting at 10:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 19

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 215M (cubic metre) slab concrete pour at level 59, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, September 20

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 59 – 60, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, September 21

  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 59 – 60, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

L Tower very close to topping off

The L Tower is very close to topping off. Currently at the 58th floor which will be the last one to be occupied. Everything above floor 58 is mechanical. The week of Septemebr 17 will see the 59th floor poured.

For more on this story, and more pictures, please click on this link to the Ctiyzen Developments Blog.

L Tower close to being topped off.

L Tower updated for September 14

An L Tower construction update for Friday, September 14, 2012 has been posted in L Tower Construction Schedule September 8 – 14

Friday, September 14

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
      1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
      2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

L Tower updated for September 13

An L Tower construction update for Thursday September 13 has been posted in L Tower Construction Schedule September 8 – 14

Thursday, September 13

  • There will be a 12M (cubic metre) concrete pour starting at 2:00 pm, which is expected to be finished prior to 7:00 pm. 

L Tower Construction Schedule September 8 – 14

This is the current construction schedule for 8 The Esplanade – L Tower – for September 8 – 14, 2012

UPDATED September 12, 2012

Saturday, September 8

  • A delivery of 4 containers of window curtain wall, to arrive after 9:00 am. 

Monday, September 10 

  • A delivery of drywall studs starting at 8:00 am. 
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 58 – 59, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, September 11

  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 12

  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, September 13

  • There will be a 12M (cubic metre) concrete pour starting at 2:00 pm, which is expected to be finished prior to 7:00 pm. 

Friday, September 14

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
      1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
      2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A delivery of a pressurization fan, starting at 9:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Backstage Construction Schedule – September 10 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 10 – 14, 2012

Posted September 7, 2012

Monday, September 10 

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Tuesday, September 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 13

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 14

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Revised L Tower Construction Schedule Sept 4 – 7

Please note that the construction schedule for the L Tower has been revised, due to weather conditions, for the week of September 4 – 7, 2012.

Click here for the updated posting.

Or download this revised PDF SummaryRevised L Tower – Backstage Construction Sept 4-7