L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: