Backstage Construction Schedule – October 1 – 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 1 – 5, 2012

Posted September 28, 2012

Monday, October 1 

  • Hydraulic breaking of the shale.
  • Tentative – Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, October 2 

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 3

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 4

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 5

  • Hydraulic breaking of the shale.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: