Backstage Construction Schedule – September 24 – 28
September 27, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 24 – 28, 2012
Updated September 27, 2012
Monday, September 24 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm
- The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
- Wide-load delivery with police escort, via Scot Street, expected after 10 am, depending on traffic conditions.
- Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **
Tuesday, September 25
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **
Wednesday, September 26
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **
Thursday, September 27
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **
Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm
- The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
- Subcontractor C&M McNally will be continuing work to complete the stainless steel tunnel lining. *
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **
NOTES:
* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed.
** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28