Backstage Construction Schedule – September 17 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 17 – 21, 2012

Updated September 16, 2012

NOTE: Further details on the daytime road closures will be posted on Monday, September 17

Monday, September 17 

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, September 18 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions. 
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Wednesday, September 19 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Thursday, September 20 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Friday, September 21– Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. * 
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: