L Tower Construction Schedule September 17 – 21

This is the current construction schedule for 8 The Esplanade – L Tower – for September 17 – 21, 2012

Updated September 18, 2012

Monday, September 17 

  • A delivery of heat pumps at 7:00 am. 
  • A second delivery of heat pumps at 10:00 am. 
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, September 18

  • A delivery of drywall and metal studs starting at 8:00 am.
  • A second delivery of drywall and metal studs starting at 10:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 19

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 215M (cubic metre) slab concrete pour at level 59, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, September 20

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 59 – 60, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, September 21

  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 59 – 60, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: