L Tower Construction Schedule September 8 – 14

This is the current construction schedule for 8 The Esplanade – L Tower – for September 8 – 14, 2012

UPDATED September 12, 2012

Saturday, September 8

  • A delivery of 4 containers of window curtain wall, to arrive after 9:00 am. 

Monday, September 10 

  • A delivery of drywall studs starting at 8:00 am. 
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 58 – 59, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, September 11

  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 12

  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, September 13

  • There will be a 12M (cubic metre) concrete pour starting at 2:00 pm, which is expected to be finished prior to 7:00 pm. 

Friday, September 14

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
      1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
      2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A delivery of a pressurization fan, starting at 9:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: