L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Backstage Construction Schedule – October 1 – 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 1 – 5, 2012

Posted September 28, 2012

Monday, October 1 

  • Hydraulic breaking of the shale.
  • Tentative – Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, October 2 

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 3

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 4

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 5

  • Hydraulic breaking of the shale.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

REMINDER – Backstage Construction Update

Posted September 27, 2012

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Subcontractor C&M McNally will be continuing work to complete the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage Construction Schedule – September 24 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 24 – 28, 2012

Updated September 27, 2012

Monday, September 24 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Wide-load delivery with police escort, via Scot Street, expected after 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Tuesday, September 25 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Wednesday, September 26 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Thursday, September 27 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Subcontractor C&M McNally will be continuing work to complete the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28

L Tower Construction Schedule September 24 – 28

This is the current construction schedule for 8 The Esplanade – L Tower – for September 24 – 28, 2012

Posted September 21, 2012

Monday, September 24

  • A delivery of four (4) containers of glass from  7:00 am through 4:00 pm.
  • A second delivery of HVAC units at 7:00 am. 
    • Please note:
            1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
            2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • Curbs concrete pour starting at approximately 2:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, September 25

  • A delivery of door hardware from subcontractor CityWide at 10:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 26

  • To Be Determined – the website will be updated once information is available.

Thursday, September 27

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, September 28

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28

Esplanade Road Closure Update: Open Sept 20. Closed Sept 21 and 24

The Esplanade between Scott Street and Yonge Street was open today, September 19 and will be open tomorrow September 20. It will be closed again on Friday, September 21 and Monday September 24.

The cause of this change as noted in a previous post (here), were the transportation and wide-load delivery challenges for the steel lining that was to be installed, starting on Tuesday, September 18. Initial preparations were done on Tuesday with the mobile crane. However, without the steel lining no further work could be done.

Mobile Crane on The Esplanade, September 18/12

This delay and rescheduling has been caused by factors beyond the control of the construction management team. They apologize again for the inconvenience these changes may cause.


The revised plan will not exceed the original number of permitted road closure days and stays within the permitted hours – 7 am – 6 am.

UPDATE as of September 19, 2012

Road Closure: The Esplanade between Scott Street and Yonge Street:

  • Thursday, September 20 – OPEN
  • Friday, September 21, CLOSED 7 am – 6 pm
  • Monday, September 24, CLOSED 7 am – 6 pm

Wide-load Deliveries under police escort 

  • Friday, September 21 – after 10 am.
  • Monday, September 25 – after 10 am

    Please click on this link for a downloadable PDF version of this post: Esplanade Road Closure Update

Transportation & Delivery Issues Impact Backstage today.

The expected Wide-Load steel delivery was CANCELLED today, September 18, due to traffic and transportation issues beyond the control of the construction management team.

This serious transportation and delivery issue may impact the deliveries planned for September 19 – 21st. This may involve canceling some or all of the remaining daytime (7 am – 6 pm) road closure for September 19 – 21 and rescheduling it. 

We will update information regarding planned deliveries and the road closure for September 19 – 21 as soon as it becomes available.

Revised L Tower Construction Schedule Sept 17 – 21

Please note that the construction schedule for the L Tower has been revised, due to weather conditions, for the week of September 17 – 21, 2012.

Click here for the updated posting.

 

Wide-load steel deliveries to Backstage Sept 18 – 21

Wide-Load CANCELLED due to traffic and transportation issues — Please note that there will be wide-load steel deliveries under police escort to the Backstage construction site each morning from September 18 – 21 — We will update information regarding September 19 -21 as soon as it becomes available. 

  • These deliveries will be made to the site at 1 The Esplanade, via Scott Street, during the daily — September 18 – 21, 7 am to 6 pm — road closure period.
  • We expect the loads will arrive between 7 am and 10 am depending on traffic and road conditions.
  • We will update this information if there are changes to the delivery schedule or as new information becomes available.

The construction  management team apologizes for any inconvenience. All efforts will be made to ensure that this work is carried out as efficiently as possible. 

Daytime Road Closures September 18 – 21

Please note a serious transportation and delivery issue has prevented the steel delivery today September 18. This may impact the road closure. We will update this information as soon as we can.  

 

There will be daytime road closures of The Esplanade between Scott and Yonge streets September 18 – 21. These are required to ensure public safety during the unloading and installation of the stainless steel tunnel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed.

The construction management team apologizes for the inconvenience. If possible the road closures will be opened prior to 6 pm if the daily work has been completed. 

More detailed information will be posted on Monday, September 17.

Please click here for the current daily schedule for the Backstage and L Tower parking construction site. 