L Tower Construction Schedule September 4 – 7

This is the current construction schedule for 8 The Esplanade – L Tower – for September 4 – 7, 2012

Updated September 4, 2012

Monday, September 3 – Labour Day – Holiday

Tuesday, September 4

  • Cancelled due to rain: A 9M (cubic metre) column concrete pour, levels 57 – 58, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
  • Deliveries cancelled. 
Wednesday, September 5

  • Subcontractor Cooltech delivering HVAC components starting at 7:00 am. 
  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
      1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
      2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  •  A 4M (cubic metre) column concrete pour, levels 57 – 58, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, September 6

  • 215M (cubic metre) slab concrete pour at level 58, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, September 7

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 58 – 59, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: