Backstage Construction Schedule – September 4 – 7
August 31, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 4 – 7, 2012
Posted August 31, 2012
Monday, September 3 – Labour Day – Holiday
Tuesday, September 4
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be installing rock anchors.
Wednesday, September 5
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be will be installing rock anchors.
Thursday, September 6
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be installing rock anchors.
Friday, September 7
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be installing rock anchors.
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.