L Tower Construction Schedule August 25 – 31

This is the current construction schedule for 8 The Esplanade – L Tower – for August 25 – 31.

UPDATED August 27, 2012

Saturday, August 25

  • Hoist maintenance.

Monday, August 27

  • CANCELLED DUE TO RAIN: A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am,  which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, August 28

  • A rebar (steel) delivery starting at 10:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, August 29

  • A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am,  which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, August 30

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 57 – 58, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • The man and material hoist to be lifted 3 floors to level 51.

Friday, August 31

  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 57 – 58, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.

NOTES:
Construction schedules are dependent on weather conditions.

RESCHEDULED TO TUESDAY September 4:

            • A 215M (cubic metre) slab concrete pour at level 58, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: