L Tower Construction Schedule August 25 – 31
August 24, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for August 25 – 31.
UPDATED August 27, 2012
Saturday, August 25
- Hoist maintenance.
Monday, August 27
- CANCELLED DUE TO RAIN: A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 10:00 am.
- Please note:
- There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
Tuesday, August 28
- A rebar (steel) delivery starting at 10:00 am.
- A rebar (steel) delivery starting at 12:30 pm.
- Please note:
- There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
Wednesday, August 29
- A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 12:30 pm.
- Please note:
- There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
Thursday, August 30
- There will be a rebar (steel) delivery starting at 7:00 am.
- A rebar (steel) delivery starting at 12:30 pm.
- Please note:
- There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
- A 96M (cubic metre) part one (1), wall and column concrete pour, levels 57 – 58, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.
- The man and material hoist to be lifted 3 floors to level 51.
Friday, August 31
- A rebar (steel) delivery starting at 10:00 am.
- Please note:
- There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
- To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
- A 92M (cubic metre) part two (2), wall and column concrete pour, levels 57 – 58, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
NOTES:
Construction schedules are dependent on weather conditions.
RESCHEDULED TO TUESDAY September 4:
- A 215M (cubic metre) slab concrete pour at level 58, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31