L Tower Construction Schedule August 18 – 24

This is the current construction schedule for 8 The Esplanade – L Tower – for August 18th to 24th

Posted August 17, 2012

Saturday, August 18

  • There will be a crane mast extension.

Monday, August 20

  • A rebar (steel) delivery starting at 7:00AM and 12:30PM.

Tuesday, August 21

  • A rebar (steel) delivery starting at 10:00 am.
  • A 215M (cubic metre) slab concrete pour at level 56, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, August 22

  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 56 – 57, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, August 23

  • A 92M (cubic metre) part 2, wall and column concrete pour, levels 56 – 57, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
  • There will be a rebar (steel) delivery starting at 12:30 pm.

Friday, August 24

  • A rebar (steel) delivery starting at 7:00AM and 12:30PM

NOTES:
Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: