L Tower Construction Schedule August 11 – 17

This is the current construction schedule for 8 The Esplanade – L Tower – for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street

Saturday, August 11

  • There will be a crane mast extension, with two mast sections added

Monday, August 13

  • A rebar (steel) delivery at 12:30 pm.
  • A 70M (cubic metre) slab concrete pour, level 54 to 55, starting 1:00 pm, which is expected to finish prior to 7:00 pm.

Tuesday, August 14

  • A rebar (steel) delivery at 7:00 am and 12:30 pm.

Wednesday, August 15

  • There will be a 160M (cubic metre) slab concrete pour, level 55, starting 9:00 am, which is expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery at 10:00 am.

Thursday, August 16

  •  A 110M (cubic metre) part 1, wall and column concrete pour, levels 55 – 56, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, August 17

  • A rebar (steel) delivery starting at 12:30 pm.
  • A 63M (cubic metre) part 2, wall and column concrete pour, levels 55 – 56, starting at 1:o0 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: