Backstage Construction Schedule – August 13 – August 17
August 10, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 11 – August 17, 2012
Updated August 13, 2012
PLEASE NOTE:
- The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street.
Monday, August 13
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Tuesday, August 14
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Wednesday, August 15
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Thursday, August 16
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Friday, August 17
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17