L Tower Construction Schedule September 4 – 7

This is the current construction schedule for 8 The Esplanade – L Tower – for September 4 – 7, 2012

Updated September 4, 2012

Monday, September 3 – Labour Day – Holiday

Tuesday, September 4

  • Cancelled due to rain: A 9M (cubic metre) column concrete pour, levels 57 – 58, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
  • Deliveries cancelled. 
Wednesday, September 5

  • Subcontractor Cooltech delivering HVAC components starting at 7:00 am. 
  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
      1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded.
      2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  •  A 4M (cubic metre) column concrete pour, levels 57 – 58, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, September 6

  • 215M (cubic metre) slab concrete pour at level 58, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, September 7

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery will commence at at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 58 – 59, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

Backstage Construction Schedule – September 4 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 4 – 7, 2012

Posted August 31, 2012

Monday, September 3 – Labour Day – Holiday 

Tuesday, September 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

Revised L Tower Construction Schedule – August 28 – 31

Please note that the construction schedule for the L Tower has been revised as of today for the balance of the week – August 28 – 31, 2012. Please click here for the revised schedule. 

L Tower Construction Schedule August 25 – 31

This is the current construction schedule for 8 The Esplanade – L Tower – for August 25 – 31.

UPDATED August 27, 2012

Saturday, August 25

  • Hoist maintenance.

Monday, August 27

  • CANCELLED DUE TO RAIN: A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am,  which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, August 28

  • A rebar (steel) delivery starting at 10:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, August 29

  • A 215M (cubic metre) slab concrete pour at level 57, starting at 9:00 am,  which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, August 30

  • There will be a rebar (steel) delivery starting at 7:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 57 – 58, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • The man and material hoist to be lifted 3 floors to level 51.

Friday, August 31

  • A rebar (steel) delivery starting at 10:00 am.
    • Please note:
        1. There will be short-term disruptions to vehicular traffic while the steel delivery truck is being unloaded. 
        2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 92M (cubic metre) part two (2), wall and column concrete pour, levels 57 – 58, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.

NOTES:
Construction schedules are dependent on weather conditions.

RESCHEDULED TO TUESDAY September 4:

            • A 215M (cubic metre) slab concrete pour at level 58, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Backstage Construction Schedule – August 27 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 27 – 31, 2012

Posted August 24, 2012

Monday, August 27

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 28

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be bringing in a rock anchor drill and beginning to install the last row of tie backs.
    • Please Note: there may be disrutions to pedestrian and vehicualr traffic during the delivery and unloading of the drill.

Thursday, August 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

Friday, August 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Backstage Construction Schedule – August 20 – August 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 20 – August 24, 2012

Posted August 17, 2012

Monday, August 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

L Tower Construction Schedule August 18 – 24

This is the current construction schedule for 8 The Esplanade – L Tower – for August 18th to 24th

Posted August 17, 2012

Saturday, August 18

  • There will be a crane mast extension.

Monday, August 20

  • A rebar (steel) delivery starting at 7:00AM and 12:30PM.

Tuesday, August 21

  • A rebar (steel) delivery starting at 10:00 am.
  • A 215M (cubic metre) slab concrete pour at level 56, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.

Wednesday, August 22

  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 56 – 57, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, August 23

  • A 92M (cubic metre) part 2, wall and column concrete pour, levels 56 – 57, starting at 12:30 pm, which is not expected to extend beyond 7:00 pm.
  • There will be a rebar (steel) delivery starting at 12:30 pm.

Friday, August 24

  • A rebar (steel) delivery starting at 7:00AM and 12:30PM

NOTES:
Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

The Esplanade is Now Open – Scott Street to Yonge Street

 

The Esplanade from Yonge Street to Scott Street

Posted August 13, 2012

We are pleased to announce that The Esplanade has reopened to vehicles travelling Eastbound from Yonge Street to Scott Street and for pedestrians travelling in East and West.

We would like to thank all members of the neighbourhood and the local businesses for your patience and understanding during this time. The construction was completed within the allotted time of the permit from the City of Toronto. We do hope that the free shuttle service was an assistance while The Esplanade was temporarily closed.

Thank you as well to those who provided feedback and suggestions through this website and our email newsletter.

L Tower Construction Schedule August 11 – 17

This is the current construction schedule for 8 The Esplanade – L Tower – for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street

Saturday, August 11

  • There will be a crane mast extension, with two mast sections added

Monday, August 13

  • A rebar (steel) delivery at 12:30 pm.
  • A 70M (cubic metre) slab concrete pour, level 54 to 55, starting 1:00 pm, which is expected to finish prior to 7:00 pm.

Tuesday, August 14

  • A rebar (steel) delivery at 7:00 am and 12:30 pm.

Wednesday, August 15

  • There will be a 160M (cubic metre) slab concrete pour, level 55, starting 9:00 am, which is expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery at 10:00 am.

Thursday, August 16

  •  A 110M (cubic metre) part 1, wall and column concrete pour, levels 55 – 56, starting at 1:00 pm, which is not expected to extend beyond 7:00 pm.

Friday, August 17

  • A rebar (steel) delivery starting at 12:30 pm.
  • A 63M (cubic metre) part 2, wall and column concrete pour, levels 55 – 56, starting at 1:o0 pm, which is not expected to extend beyond 7:00 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17

Backstage Construction Schedule – August 13 – August 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street.

Monday, August 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 16

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17