L Tower Construction Schedule July 30 – August 3
July 29, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for July 30 – August 3, 2012
Revised July 31, 2012
PLEASE NOTE:
- The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect this week
- A shuttle bus service will be provided during the road closure running approximately every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott Street to Union Station, Bay & Front, King & Yonge and Berczy Park.
- For a PDF Copy: L Tower Community Shuttle Bus Route – MAP
Monday, July 30
- Yuanda delivery of three (3) containers of windows, starting at 7:00 am.
- A rebar (steel) delivery starting at 7:00 am.
- A second rebar (steel) delivery starting at 12:30 pm
Tuesday, July 31
- Scheduled Construction Activities Rescheduled Due To Weather Conditions.
Wednesday, August 1
- A rebar (steel) delivery starting at 10:00 am.
- A 215M (cubic metre) slab concrete pour, at level 53, starting at 11:00 am, which is not expected to extend beyond 7:00 pm.
Thursday, August 2
- Primo Mechanical delivery of Heat Pumps for levels 36 to 40, scheduled to begin at &;30 am and be completed by 11:00 am.
- A 96M (cubic metre) part one (1), wall and column concrete pour, levels 53 – 54, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 12:30 pm.
Friday, August 3
- A rebar (steel) delivery starting at 7:00 am.
- A 92M (cubic metre) part 2, wall and column concrete pour, levels 53 – 54, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- A second rebar (steel) delivery starting at 12:30 pm.
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: Construction Summary July 30 – August 3