Backstage Construction Schedule – July 30 – August 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 30 – August 3, 2012

Updated July 31, 2012

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.

Monday, July 30

  • Sub-contractor, C & M McNally boring the tunnel.
  • The tunnel connects the P4 parking level on the Backstage site at 1 The Esplanade with the L Tower. All L Tower residents will use this private tunnel to access their parking spaces which will be located underneath the future Backstage condominium.  
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, July 31

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 1

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 2 

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 3

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

RESCHEDULED to August 9: Sub-contractor, C & M McNally will be removing the Tunnel Boring Machine from the site with a 500-ton crane.

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary July 30 – August 3

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: