L Tower Construction Schedule July 21 – 27

This is the current construction schedule for 8 The Esplanade – L Tower – for   July 21 – 27, 2012

Revised July 26, 2012

PLEASE NOTE:

Saturday, July 21

  • Hoist maintenance.
  • Yuanda delivery of three (3) containers of windows. 

Monday, July 23

  • A rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery starting at 12:30 pm

Tuesday, July 24

  • A 215M (cubic metre) slab concrete pour, at level 52, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, July 25

  • A 96M (cubic metre) part 1, wall and column concrete pour, levels 52 – 53, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, July 26 – Concrete Pour & Rebar deliveries Cancelled due to weather conditions. 

Friday, July 27 – REVISED

  • A rebar (steel) delivery starting at 7:00 am.
  • A 92M (cubic metre) part 2, wall and column concrete pour, levels 52 – 53, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • A second rebar (steel) delivery starting at 12:30 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction July 21-27

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

<span>%d</span> bloggers like this: