L Tower Construction Schedule July 21 – 27
July 24, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for July 21 – 27, 2012
Revised July 26, 2012
PLEASE NOTE:
- The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect this week
- A shuttle bus service will be be provided during the road closure please click here for the route map for the shuttle bus service.
- Please click on this link for a PDF Map of of the shuttle bus route: L Tower Community Shuttle Bus Route – MAP
- Please click here for copy of the road closure notice: NOTICE-Road Closure
- Please click on this link for a copy of the City of Toronto Temporary Street Occupation Permit: 8 The Esplanade Temporary Street Occupation Permit
Saturday, July 21
- Hoist maintenance.
- Yuanda delivery of three (3) containers of windows.
Monday, July 23
- A rebar (steel) delivery starting at 7:00 am.
- A second rebar (steel) delivery starting at 12:30 pm
Tuesday, July 24
- A 215M (cubic metre) slab concrete pour, at level 52, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 12:30 pm.
Wednesday, July 25
- A 96M (cubic metre) part 1, wall and column concrete pour, levels 52 – 53, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
Thursday, July 26 – Concrete Pour & Rebar deliveries Cancelled due to weather conditions.
Friday, July 27 – REVISED
- A rebar (steel) delivery starting at 7:00 am.
- A 92M (cubic metre) part 2, wall and column concrete pour, levels 52 – 53, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- A second rebar (steel) delivery starting at 12:30 pm.
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower & Backstage Construction July 21-27