Backstage Construction Schedule – July 16 – 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 16 – 20, 2012

Posted July 13, 2012

Monday, July 16

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Tuesday, July 17

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Wednesday, July 18

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Thursday, July 19

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Friday, July 20

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

* * *

Excavating the site at 1 The Esplanade

 NOTES:

 A Paid Duty Police Officer is
on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: