L Tower Construction Schedule July 7 – 13
July 6, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for July 7 – 13, 2012
Posted July 6, 2012
PLEASE NOTE:
- The L Tower is scheduled to reach 50 floors this week.
- The 30 day road closure of The Esplanade from Scott Street to Yonge Street is scheduled to begin on July 16. Notices and information will be posted on this website and circulated to local businesses and residents July 12 – 13.
Saturday, July 7
- Yuanda window delivery starting at 9:00 am.
Monday, July 9
- Yuanda window delivery starting at 7:00 am (conditional).
Tuesday, July 10
- A 96M (cubic metre) part 2, wall and column concrete pour, levels 49 – 50, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
- Please click here for a recent photograph of a midday rebar (steel) delivery.
Wednesday, July 11
- A rebar (steel) delivery starting at 7:00 am.
- A second rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
- Please click here for a recent photograph of a midday rebar (steel) delivery.
Thursday, July 12
- A 215M (cubic metre) slab concrete pour, at level 50, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
Friday, July 13
- A 92M (cubic metre) part 1, wall and column concrete pour, levels 50 – 51, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage July 7 – 13 summary highlights: L Tower & Backstage Construction July 7-13