Backstage Construction Schedule – July 3 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 3 – 6, 2012

Updated July 2, 2012

NOTE: With 6 trucks doing 10 loads each this week there will be a greater amount of truck traffic to and from the site. Please be prepared for short-terms traffic delays as the trucks move in and out of the 1 The Esplanade gate.

For photos illustrating the current forms of work at the Backstage site please click here.

Tuesday, July 3

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Wednesday, July 4

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Thursday, July 5

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads..

Friday, July 6

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage July 3 – 6 summary highlights: L Tower & Backstage Construction July 3-6

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: