L Tower & Backstage Aug 1 – 3 Schedules REVISED

Due to inclement weather today, July 31, 2012, construction schedules at the L Tower and Backstage sites were  significantly affected. 

The construction schedules for both sites have been revised for the balance of this week, August 1 – 3. 

Please click here for the REVISED L Tower Schedule

Please click here for the REVISED Backstage Schedule

L Tower from Front & Sherbourne

image

The L Tower at 53 floors as seen from Front Street East and Sherbourne, July 30, 2012

Backstage Construction Schedule – July 30 – August 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 30 – August 3, 2012

Updated July 31, 2012

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.

Monday, July 30

  • Sub-contractor, C & M McNally boring the tunnel.
  • The tunnel connects the P4 parking level on the Backstage site at 1 The Esplanade with the L Tower. All L Tower residents will use this private tunnel to access their parking spaces which will be located underneath the future Backstage condominium.  
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, July 31

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 1

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 2 

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 3

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

RESCHEDULED to August 9: Sub-contractor, C & M McNally will be removing the Tunnel Boring Machine from the site with a 500-ton crane.

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary July 30 – August 3

L Tower Construction Schedule July 30 – August 3

This is the current construction schedule for 8 The Esplanade – L Tower – for   July 30 – August 3, 2012

Revised  July 31, 2012

PLEASE NOTE:

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect this week
  • A shuttle bus service will be provided during the road closure running approximately every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott Street to Union Station, Bay & Front, King & Yonge and Berczy Park.   

Monday, July 30

  • Yuanda delivery of three (3) containers of windows, starting at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery starting at 12:30 pm

Tuesday, July 31

  • Scheduled Construction Activities Rescheduled Due To Weather Conditions. 

Wednesday, August 1

  • A rebar (steel) delivery starting at 10:00 am.
  • A 215M (cubic metre) slab concrete pour, at level 53, starting at 11:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, August 2 

  • Primo Mechanical delivery of Heat Pumps for levels 36 to 40, scheduled to begin at &;30 am and be completed by 11:00 am. 
  • A 96M (cubic metre) part one (1), wall and column concrete pour, levels 53 – 54, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.

Friday, August 3

  • A rebar (steel) delivery starting at 7:00 am.
  • A 92M (cubic metre) part 2, wall and column concrete pour, levels 53 – 54, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • A second rebar (steel) delivery starting at 12:30 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary July 30 – August 3

L Tower July 28 Update

This is a construction update for 8 The Esplanade – L Tower – for   July 28, 2012

Posted July 28, 2012

PLEASE NOTE:

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect this week
  • A shuttle bus service will be provided during the road closure running approximately every 12 – 15 minutes from 7 am to 7 pm daily, connecting The Esplanade and Scott Street to Union Station, Bay & Front, King & Yonge and Berczy Park.   

Saturday, July 28

  • Yuanda delivery of three (3) containers of windows, starting at 9;00 am.
  • The crane mast will be extended by two sections.

L Tower & Backstage Updates for Friday July 27

These are the revised L Tower and Backstage Schedules for Friday, July 27

NOTE: There will be dump trucks, rebar deliveries and concrete trucks arriving and departing, as Thursday’s scheduled concrete pour and deliveries were cancelled due weather conditions. Thanks to the Sony Centre, trucks will have access to the Centre’s Front Street lay-by as a staging area, which will help to ease congestion on Scott Street and the Esplanade.

Friday, July 27 – REVISED

Backstage – click here to see revised original post for July 21 – 27:

  • Tunnel Boring Machine testing.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 12 -13 loads each, for a total of seventy-two to seventy-four (72 – 74) loads.

L Tower – click here to the see revised original post for July 21 – 27:

  • A rebar (steel) delivery starting at 7:00 am.
  • A 92M (cubic metre) part 2, wall and column concrete pour, levels 52 – 53, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • A second rebar (steel) delivery starting at 12:30 pm.

Update on Tunnel Boring Machine & Crane Removal

July 25, 2012

Thanks again to all of you for your patience and understanding today. The Tunnel Boring Machine is now in place photos have been previously posted to this site during the delivery and load in of the machine, and some are also below. We appreciated the opportunity to speak with several residents of 25 The Esplanade today. Their kind words were greatly appreciated.

Please note that the mobile crane used to lift the machine into place will be removed from the site by approximately 9 pm this evening. The truck used to move it needs to avoid rush hour traffic. The mobile crawler crane that will be used during the boring operation will be delivered to the site later this week. Updated details will be posted here at https://ltowerconstructioninfo.com/.

Tunnel Boring Machine arriving on The Esplanade July 25, 2012

Tunnel Boring Machine backing into position at 1 The Esplanade, July 25, 2012

Tunnel Boring Machine lifted by mobile crane in preparation for placement on-site, July 25, 2012

Tunnel Boring Machine lifted by mobile crane, July 25, 2012

Tunnel Borng Machine Lowered into place, 40 feet down, at 1 The Esplanade

Tunnel Boring Machine floating into place

image

The Tunnel Boring Machine floating into place at the Backstage site at 1 The Esplanade.

Tunnel Boring Machine lifted in

image

The Tunnel Boring Machine lifting in by crane at 1 The Esplanade.

Tunnel Boring Machine on site

image

Waiting to be off-loaded into the 40′ hole at the Backstage site at 1 The Esplanade.