L Tower Construction Schedule July 3 – 6

This is the current construction schedule for 8 The Esplanade – L Tower – for   July 3 – 7, 2012

Posted June 29, 2012

NOTE:

  • The L Tower is scheduled to reach 49 floors this week.

Tuesday, July 3

  • Yuanda window delivery starting at 7:00 am.
  • A 92M (cubic metre) part 1, wall and column concrete pour, levels 48 – 49, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, July 4

  • Yuanda window delivery starting at 7:00 am.
  • A hoist jump is scheduled for today
  • A 96M (cubic metre) part 2, wall and column concrete pour, levels 48 – 49, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:00.

Thursday, July 5

  • A rebar (steel) delivery starting at 7:00 am.
  • A second rebar (steel) delivery starting at 12:00 pm.

Friday, July 6

  • A rebar (steel) delivery starting at 10:00 am.
  • A 215M (cubic metre) slab concrete pour, at level 49, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage July 3 – 6 summary highlights: L Tower & Backstage Construction July 3-6

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: