L Tower Construction Schedule June 25 – 29

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 25 – 29, 2012

Posted June 22, 2012

NOTE:

  • The L Tower is scheduled to reach 48 floors this week.

Monday, June 25

  • A 210M (cubic metre) slab concrete pour, at level 47, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 12:00.

Tuesday, June 26

  • A 92M (cubic metre) part 1, wall and column concrete pour, levels 47 – 48, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • TORSTEEL delivery of handrails
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 27

  • A 96M (cubic metre) part 2, wall and column concrete pour, levels 47 – 48, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
  • Citywide  to deliver door frames today.
  • A rebar (steel) delivery starting at 12:00.

Thursday, June 28

  • A rebar (steel) delivery starting at 10:00 am.
  • A second rebar (steel) delivery starting at 12:00 pm.
  • UCEL will raise the hoist cables today.

Friday, June 29

  • A 210M (cubic metre) slab concrete pour, at level 48, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: