L Tower Construction Schedule June 25 – 29
June 23, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for June 25 – 29, 2012
Posted June 22, 2012
NOTE:
- The L Tower is scheduled to reach 48 floors this week.
Monday, June 25
- A 210M (cubic metre) slab concrete pour, at level 47, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 12:00.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
- Please click here for a recent photograph of a midday rebar (steel) delivery.
Tuesday, June 26
- A 92M (cubic metre) part 1, wall and column concrete pour, levels 47 – 48, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- TORSTEEL delivery of handrails
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open
Wednesday, June 27
- A 96M (cubic metre) part 2, wall and column concrete pour, levels 47 – 48, starting at 12:00 pm, which is not expected to extend beyond 7:00 pm.
- Citywide to deliver door frames today.
- A rebar (steel) delivery starting at 12:00.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
- Please click here for a recent photograph of a midday rebar (steel) delivery.
Thursday, June 28
- A rebar (steel) delivery starting at 10:00 am.
- A second rebar (steel) delivery starting at 12:00 pm.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
- Please click here for a recent photograph of a midday rebar (steel) delivery.
- UCEL will raise the hoist cables today.
Friday, June 29
- A 210M (cubic metre) slab concrete pour, at level 48, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29