Backstage Construction Schedule – June 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 25 – 29, 2012

Posted June 22, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 25

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Tuesday, June 26

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 27

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Thursday, June 28

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 29

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: