L Tower Construction Schedule June 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 18 – 22, 2012

Posted June 15, 2012

NOTE:

  • The L Tower is scheduled to reach 46 floors this week.

Monday, June 18

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Tuesday, June 19

  • A 220M (cubic metre) slab concrete pour, at level 46, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 20

  • A 122M (cubic metre) part 1, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Thursday, June 21

  • A 70M (cubic metre) part 2, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Friday, June 22

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: