L Tower Construction Schedule June 11 – 15
June 9, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for June 11 – 15, 2012
Posted June 8, 2012
NOTE:
- The L Tower is scheduled to reach 45 floors this week.
Monday, June 11
- Rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
- A 101M (cubic metre) part 2, wall and column concrete pour, levels 44 – 45, starting at 1 pm, which is not expected to extend beyond 7:00 pm.
- The hoist will be climbed (raised) three floors.
Tuesday, June 12
- A rebar (steel) delivery starting at 7:00 am.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open
- A second rebar (steel) delivery starting at 12:30.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
Wednesday, June 13
- A rebar (steel) delivery starting at 7:00 am.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open
- A 220M (cubic metre) slab concrete pour, at level 45, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
- A second rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
Thursday, June 14
- A 101M (cubic metre) part 1, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.
Friday, June 15
- A rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
- A 101M (cubic metre) part 2, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15