Backstage Construction Schedule – June 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 11 – 15, 2012

Posted June 8, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 12

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: