Backstage Construction Schedule – June 4 – 8
June 1, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for June 4 – 8, 2012
Posted June 1, 2012
NOTE:
- We have also been advised that the final phase of the Waterfront Toronto sewer construction contract will begin on Monday, June 4 for approximately 8 weeks. Jarvis Street will be reduced to one lane in each direction betweenThe Esplanade and Wilton Street.
Monday, June 4
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
- Subcontractor, Deep Foundation installing tie backs.
Tuesday, June 5
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
- Subcontractor, Deep Foundation installing tie backs.
Wednesday, June 6
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
- Subcontractor, Deep Foundation installing tie backs.
Thursday, June 7
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
- Subcontractor, Deep Foundation installing tie backs.
Friday, June 8
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
- Subcontractor, Deep Foundation installing tie backs.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage June 4 – 8 summary highlights: L Tower & Backstage Construction June 4-8