L Tower Construction Schedule May 28 – June 1
May 25, 2012 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower – for May 28 – June 1, 2012
Posted May 25, 2012
NOTE:
- The L Tower is scheduled to reach 43 floors this week.
- We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.
Monday, May 28
- A 92M (part 1) wall and column concrete pour, levels 42 – 43, starting at Noon, which is not expected to extend beyond 7:00 pm.
Tuesday, May 29
- Rebar (steel) delivery starting at Noon.
- Please note that eastbound vehicular traffic may be interrupted during this delivery.
- Pedestrian traffic will remain open.
- A 96M (part 2) wall and column concrete pour, levels 41 – 42, starting at Noon, which is not expected to extend beyond 7:00 pm.
Wednesday, May 30
- A rebar (steel) delivery starting at 7:00 am.
- A second rebar (steel) delivery starting at 12:30 pm.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
Thursday, May 31
- A 215M slab concrete pour, levels 43, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.
- A rebar (steel) delivery starting at 10:00 am.
- Please note that eastbound vehicular traffic may be interrupted during these deliveries.
- Pedestrian traffic will remain open.
Friday, June 1
- A 92M (part 1) wall and column concrete pour, levels 43 – 44, starting at Noon, which is not expected to extend beyond 7:00 pm.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1