L Tower Construction Schedule May 28 – June 1

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  28 – June 1, 2012

Posted May 25, 2012

NOTE:

  1. The L Tower is scheduled to reach 43 floors this week.
  2. We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.

Monday, May 28 

  • A 92M (part 1) wall and column concrete pour, levels 42 – 43, starting at Noon, which is not expected to extend beyond 7:00 pm.

Tuesday, May 29

  • A 96M (part 2) wall and column concrete pour, levels 41 – 42, starting at Noon, which is not expected to extend beyond 7:00 pm.

Wednesday, May 30

Thursday, May 31

  • A 215M slab concrete pour, levels 43, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

Friday, June 1

  • A 92M (part 1) wall and column concrete pour, levels 43 – 44, starting at Noon, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: