Backstage Construction Schedule – May 28 – June 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 28 – June 1, 2012

Posted May 25, 2012

NOTE: We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.

Monday, May 28 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Tuesday, May 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Wednesday, May 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Thursday, May 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Friday, June 1

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: