Backstage Construction Schedule – May 22 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 22 – 25, 2012

Posted May 18, 2012

Monday, May 21 – Victoria Day Holiday

PLEASE NOTE: Subcontractor Deep Foundation may be floating in a tie-back drill using a large semi-trailer, on Thursday May 24. Please check back for updates. 

Tuesday, May 22

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Wednesday, May 23

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Thursday, May 24

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

Friday, May 25

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each, for a total of forty (40) loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 22 – 26 summary highlights: L Tower & Backstage Construction May 22 – 26

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: