L Tower Construction Schedule May 12 – 18

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  12 – 18, 2012

Posted May 11, 2012

Note: The L Tower is scheduled to reach 41 floors this week.

Saturday, May 12

  • A floating 12M slab concrete pour, at level 4, starting 9:30 am, which is not expected to extend beyond 7:00 pm.

Monday, May 14

  • A 210M slab concrete pour, level 40, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, May 15

  • Rebar (steel) delivery starting at 12:30 pm.
  • A 101M (part 1) wall and column concrete pour, levels 40 – 41 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, May 16

  • Rebar (steel) delivery starting at 7:00 am
    • Minor disruptions to vehicular traffic may be expected. 
  • Rebar (steel) delivery starting at 12:30 pm.
  • A 101M (part 2) wall and column concrete pour, levels 40 – 41, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 17

  • The hoist will be climbed (raised) six floors (rescheduled from last week). 

Friday, May 18

  • A 220M slab concrete pour, level 41, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 12 – 18 summary highlights: L Tower & Backstage Construction May 12 – 18

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: