Backstage Construction Schedule – May 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 14 – 18, 2012

Posted May 11, 2012

Monday, May 14

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker. 

Tuesday, May 15

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Wednesday, May 16

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Thursday, May 17

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

Friday, May 18

  • Subcontractor, GFL Excavating will be removing material from the site: eight (8) dump trucks will take 5 loads each,
    for a total of forty (40) loads.
  • GFL Excavating will also be demolishing the remainder of the bridge retaining wall with a large hydraulic breaker.

* * *

NOTES:

All the piles and caissons are complete on the site.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 12 – 18 summary highlights: L Tower & Backstage Construction May 12 – 18

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: