L Tower Construction Schedule May 7 – 11

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  7 – 11, 2012

Posted May 4, 2012

Note: The L Tower is scheduled to reach 40 floors this week.

Monday, May 7

  • A 190M slab concrete pour, level 39, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.

Tuesday, May 8

  • A 99M (part 1) wall and column concrete pour, levels 39 – 40 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
  • The hoist will be raised three (3) floors, to stop at level 33.

Wednesday, May 9

  • Rebar (steel) delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 39 – 40, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 10

Friday, May 11

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 4 – 7 summary highlights: L Tower & Backstage Construction May 7 – 11

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: