Backstage Construction Schedule – May 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for May 7 – 11, 2012

Posted May 04, 2012

Monday, May 7

  • Between 9 am and 3 pm, Deep Foundation, will be “float out” the drill rig from the site at 1 The Esplanade on a large truck, under police escort.
    • Pedestrian and vehicular traffic will be impacted during this operation. 
    • Please check back on May 7 for a more precise time for the “float out.”
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 8

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 9

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 10

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

All the piles and caissons are complete on the site.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 7 – 11 summary highlights: L Tower & Backstage Construction May 7 – 11

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: