L Tower Construction Schedule April 30 – May 4

This is the current construction schedule for 8 The Esplanade – L Tower – for April 30 – May 4, 2012

Posted April 27, 2012

Note: The L Tower is scheduled to reach 39 floors this week.

Monday, April 30

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.

Tuesday, May 1

  • A 99M (part 1) wall and column concrete pour, levels 38 – 39 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, May 2

  • Rebar delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 38 – 39, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, May 3

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, May 4

  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 39, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: