L Tower Construction Schedule April 23 – 27

This is the current construction schedule for 8 The Esplanade – L Tower for April 23 – 27, 2012

Posted April 20, 2012

Note: The L Tower is scheduled to reach 38 floors this week.

Monday, April 23

  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 37, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, April 24

  • Window delivery starting at 7:00 am.
  • A 99M (part 1) wall and column concrete pour, levels 37 – 38 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, April 25

  • Rebar delivery starting at 12:30 pm. 
  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 26

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, April 27

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights:  L Tower & Backstage Construction April 23-27

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: