Backstage Construction Schedule – April 23 – 27
April 20, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 23 – 27, 2012
Posted April 20, 2012
Monday, April 23
- Subcontractor, Deep Foundation, will be removing the tie drill in the morning.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Tuesday, April 24
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Wednesday, April 25
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Thursday, April 26
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Friday, April 27
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
* * *
NOTES:
Deep Foundation will complete the pile and caisson drilling this week. The drill rig will be removed from the site once drilling is completed. Please check back for an update on the time and date of the drill rig removal.
A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights: L Tower & Backstage Construction April 23-27